Offshore Windpark Meerwind
I joined the OEM WindMW from 2012 till 2015. Initially as QA officer. involved in QA audits and Black Can inspections of Monopiles and Transition Pieces later as Assistent Packagemanager foundation and OSS. I witnessed the export cable pulling works by Prysmian and installation of the OSS with Oleg Strasnoff as Client Rep and acted as Commissioning Manager the first 6 months after installation. Initially from Jack/up Barge Thor, later from Helgoland.
Location
23 km NW from Helgoland
OEM
WindMW
Year
2014
Size
80 x 3,6 MW
SCALA
38,500 m²
Export cables pulled, gangway leads to a JUB of Seajcks that was hired by Tennet to enable cable pulling before OSS installation. Infield cable were already pulled in earlier stage.
Prysmian HV joints pre/installed under the lower deck of OSS.